Re: More than 500000 WBS elements in one single Project.

$
0
0

Hello Satyanarayana,

 

As per the Business case you just mentioned do use the activity and activity elements

I assume all procurement for the work related happens entirely for the Project and not activity based

 

But the tracking and Progress of work can be realized with activities

You can then avoid using These many WBS

 

 

 

Regards

Vittal