Hello All,
Thank you for the input
But I am still confused if we must map all the materials of the plant to the networks in CN08 or not
Example:
A plant has 10000 materials
on an average a sale order contains 200 of these materials line item wise in one order alone
we would have 1 standard network and project assigned to it
My question is should i map all 10000 materials to 1 network using LSMW or another program?
Also, should all the materials have strategy 85?
Please suggest
Thanks
Prasad