Hi Ken,
Sorry for late reply, was extremely busy.
In KKA2 transaction, after entering selection parameters, in drop down only "Display Result Analysis" shows data, all other options in drop down shows nothing.
Display Result Analysis shows:
and below is OKG5 configuration
1. Is there a way to see the detailed breakup of KKA2, particularly planned cost.
2. There is a drop ship PO and the value of it is close to the difference in CN41N & KKA2 Planned Costs.We are maintaining drop ship planned cost in CJ40. I guess, KKA2 is calculating drop ship planned cost twice. I noticed there is no configuration for LID THP-Third Party Costs, would that be affecting the planned cost somehow ?
Thanks for your help
Regards
Amit