Re: need validation in PS(workcenter) to prevent using it in any...
My system is also like that. I tried but could not succeed in enabling the same. No relevant SAP Note seen.
View ArticleSettlement Profile & Allocation Structures
Hello All, I have configured Profile and Structures as needed for the Split in to 50/50 PSG and GL. Now I have to test it. Can someone please guide me how i should test this. User doesn't want to use...
View ArticleRe: need validation in PS(workcenter) to prevent using it in any...
Hi ismail Please Check Change status of Work Center - Toolbox for IT Groups for activate user status.
View ArticleRe: SAP PS Certification C_TPLM22_64
Hi Abhishek, If you are experienced than focus on scenario based question as much you can think or depend on your experience. if you are not experienced than focus on books provided and SCN posts in...
View Articlesettlement Rule CJ03 BAPI
Hi Expert, I am try to get BAPI name for WBS settlement rule in CJ03.. finally I got the remaining details from BAPI_PROJECT_GETINFO. But when I click on settlement rule for particular WBS Element...
View ArticleDelivery from Projects without Stock in CNS0
Hello Gurus, I have a Scenario at ongoing implementation in my project where requirement is to create Delivery from Projects in CNS0. Now the case is the Machine to be manufactured is fully...
View ArticleRe: settlement Rule CJ03 BAPI
Hi Pranav, Have you tried the IMG document in path spro>project system>cost>Automatic & periodic allocation>Settlement >Settlement Rule for WBS>Business Add-in :generation for WBS...
View ArticleRe: Project stock in Inventory
Account Assignment P is used for direct consumption (Non-Valuated Project Stock). Look in your Project Definition and see what inventory you have selected, Valuated or Non-Valuated. With Valuated...
View ArticleRe: Settlement Profile & Allocation Structures
Hello, Anyone... Pls advice. How to test settlement profile/Allocation structures? Thank you,nr.
View ArticleRe: Settlement Profile & Allocation Structures
Hi, To test the settlement you should do the following1. Post some actual cost to WBS or NWA using PO/GR. Or Time Sheets or FI postings or activity confirmation2.Post some revenue.3. Assign settlement...
View ArticleRe: Close and Close technically
Thanks for the information Venkat. For anyone else who would like information, it can be found here: System Statuses in Work Breakdown Structures - Structures - SAP Library Thanks,Nick
View ArticleRe: Planned cost in KKA2 is different than CN41N
Hi Ken, Sorry for late reply, was extremely busy. In KKA2 transaction, after entering selection parameters, in drop down only "Display Result Analysis" shows data, all other options in drop down shows...
View ArticleRe: AVAC not being activated in S/4 HANA
The Budget Profile settings and Tolerance Limit is shown below
View ArticleUnable to generate automatic settlement rules to superior WBS
Hi I am unable to generate automatic settlement rule automatically from lower levels to the superior ones through implementing Note 211324 This is the error The project structure looks like this Can...
View ArticleRe: Standard SD Order with account assignment is a WBS element status "Not...
Hi Pelayo, Kindly refer to below link and see the process of handling sales order in PS Project System (PS) - SAP Library Here you have multiple business scenarios, so this will help you to do the...
View ArticleRe: Unable to generate automatic settlement rules to superior WBS
Hi Suman, Your Level 1 should settle to a different receiver then WBS.. but it looks like the strategy defined is wrong.. Can you share the settlement strategy used for settling of the top level wbs.....
View ArticleRe: Budget available in WBS but popping budget exceeded error
Hi Esha, Do you have warning message to the Person Responsible in your tolerance limits? If yes, please maintain the person responsible in your WBS.. Also as mentioned by Paulo, check the availability...
View Article