Hi,
System will consume budget from PR itself. 130 is PR commitment and out of it PO created for 85. Now, the PR commitment will be 45 only and 85 is PO commitment.
If you dont want PR commitment to consumed allocated budget then you have to implement SAP notes 955106 & 955107.
Please search in forum for more details on it.
Regards
Saurabh