Re: Formula tab to calculate quantites in service activity
Hi Byalya, Could you find a solution to this problem? I am facing a similar situtation and the formula tab just would not come! Regards,Soumyadeep Paul
View ArticleRe: Qty. of Activities in PS
Hi Shashi, Could you find a solution to this problem? I am facing a similar situation and would very much appreciate your help. Regards,Soumyadeep Paul
View ArticlePR value is 130 , PO value is 85 - but budget exceeded
Dear All , The Service PR Value is 130 but PO was created for 85 only. But Budget is blocked for 130. When I checked in CJ33 -- Availability Control Analysis. Its shows 130 only. Any solution other...
View ArticleRe: PR value is 130 , PO value is 85 - but budget exceeded
Dear All, I think we will have to TECO the Activity. But still it allows SES Regards,Shareeq
View ArticleRe: PR value is 130 , PO value is 85 - but budget exceeded
Hi,System will consume budget from PR itself. 130 is PR commitment and out of it PO created for 85. Now, the PR commitment will be 45 only and 85 is PO commitment.If you dont want PR commitment to...
View ArticleRe: PR value is 130 , PO value is 85 - but budget exceeded
Hi,System will consume budget from PR itself. 130 is PR commitment and out of it PO created for 85. Now, the PR commitment will be 45 only and 85 is PO commitment.If you dont want PR commitment to...
View ArticleRe: CJE0 REPORT actual cost is inaccurate
HI Satya, Please have a look in the below link. Difference between the Reports : S_ALR_87013558 & CJI3 RegardsRaj
View ArticleRe: RPSCO entries getting deleted after CJEN
Hi Raja, Thanks for your reply,your post is very helpful when i am looking in the log of CJEN it is giving me some warning message,No value category could be determined for commitment item 0100 XXXX...
View ArticleRe: RPSCO entries getting deleted after CJEN
HI Sandeep, Can you please check 144169 & its settings. RegardsRaj
View ArticleRe: RPSCO entries getting deleted after CJEN
Hi Sandeep, get the cost element group which you assigned in relevant value category in Txn OPI2 and ensure that cost element assignment in the cost element group in txn kah2.Regards,
View ArticleRe: CJE0 REPORT actual cost is inaccurate
Hi Satya, when you define cost element you define if it is a cost element category 1 ( primary cost/reducing revenue) or cost element category 11 ( revenue). I suppose you are using cost element...
View ArticleRe: RPSCO entries getting deleted after CJEN
Hi, I have checked in OPI2 and KAH2 , values are same.I just wanted to check that element group which we give in planning profile have any relationship with element group which we assign in value...
View ArticleRe: Error "Service does not exist" in CAT2
Check the Personnel Record of the contractor in Info Type 315. Verify the PO and Service Master specified there are still valid. The PO might have been changed or the Service Master might have been...
View ArticleRe: In BPO at the time of selecting material as category M it is taking as...
What is in the BPO header?
View ArticleRe: Cost analysis of FG item in non valuated project stock scenario.
In Non-Valuated Project Stock all account assigned PO charges are directly posted to the WBS element and not to the Production Order. The total costs will have to be analyzed from the WBS and not the...
View ArticleRe: Cost analysis of FG item in non valuated project stock scenario.
If you want to use standard SAP you'll have to switch to Valuated Project Stock.
View ArticleSet a particular user status for a WBS when system status is set to Closed...
Hello Gurus, I have a project requirement in which I have to enable the system to automatically set a particular user status for a WBS on setting system status to either "Mark for deletion" (DLFL) or...
View ArticleSetting for Cost Planning
HiCan anybody please let know what is the use of Remainder Translation in the planning profile (t-code opsb). Thanks & RegardsSatish