Re: CJI3 and CJI5 Table To fetch Actual and Commitment Value.
NO network and activities .only wbs are used.
View ArticleRe: CJI3 and CJI5 Table To fetch Actual and Commitment Value.
Hi Bheesham, Standard report show composite values : WBS L1 122WBSL2 1000 so report will show like in CJI3:if you check for WBSL1 than this report will show 1122 as total. please check. if...
View ArticleRe: 12KAT1A issue
Hi Sunil.. still i am not able to get any clue. Hello Experts, Can any body, who has idea on 12KST1A, please help me to get RemOrd Plan in object currency. After doing copy all values are populating...
View ArticleRe: 12KAT1A issue
Hi Sreenivas, have you selected object currency as i asked. if yes than you will get object currency link on left side of this report. just double click on that you will get data. hope this helps you....
View ArticleRe: 12KAT1A issue
Yes Sunil, I have selected this for RemOrder Plan. But still values are showing ZERO
View ArticleRe: 12KAT1A issue
Hi Sreenivas, Please share screens of all setting made you you from start. thanksSunil
View ArticleRe: 12KAT1A issue
Dear Sunil, The screen shots as follows Budget : Actual : Comittment : RemOrd Plan: Rest of the rows, the screen shots as follows After that, i tried to change the RemOrder Plan individial cell...
View ArticleHow to add a new WBS Element to Existing Project using BAPI_PROJECT_MAINTAIN?
Hi Friends, I have created a Project 'ABC' with WBS elements as like below ABC |____1 | |_1.1 | |_1.2 | |_1.3 |____2...
View ArticleVendor Payment Report
Hi, I need to create a report towards the payments to vendors and i suggested for CJIA, but that is not providing the desired output like Taxes and LC Amount. Please let me know if do we have any...
View ArticleRe: Attaching a document in SAP PS Network-External Activity
Hi Srini, You need to understand that PO and External activity are different objects in SAP under different domains.. You cannot pull data of external activity ( Documents/links) into PO.. if you do...
View ArticleRe: 12KAT1A issue
This is trial and error as mentioned by Sunil. Try just having "object currency" and nothing else, and see what happens. And also check against any other standard and non-standard reports too,...
View ArticleRe: S_ALR_87013558 & CJ31 assigned values not matching.
Thank you guys, I checked but still not able to figure out the root cause. Please help me out to undertstand this problem. Thanks,Vindhesh
View ArticleCJI5 doesnt show correct commitment after invoice.
Hi Experts, Here system shows something unexpected, please help me to understand this situation. We analyzed and found commitment value didn’t get reduced even though Invoice (3144.49 $) for that (PO#...
View ArticleRe: CJI5 doesnt show correct commitment after invoice.
HI vindeshPlease share the details of PO (snapshot of header and item level purchase order history)Thanks Rahul
View ArticleRe: Attaching a document in SAP PS Network-External Activity
Hi Srini, I am not sure how big is the document, you can check with PS text, whether you can incorporate any text for the link or actual text. Then check whether this text can be captured in PR Item...
View ArticleRe: CJI5 doesnt show correct commitment after invoice.
Hi Rahul, Please see the screenshot, but here values cant be seen as in production system here we cant see and need to see it thorugh tables or reports. Let me know if any other info is required, for...
View ArticleRe: How to add a new WBS Element to Existing Project using...
Hi Sunil, Thanks for your reply.I have tried with WBS_LEFT and WBS_UP,but i couldn't achieve.If you don't mind can you please let me know how to fill the entries for creating the WBS element (1.1.1)...
View ArticleRe: Attaching a document in SAP PS Network-External Activity
Hi Srini, Its very much possible using 2 methods, 1. Create PS text with Work Format to External activity. - Its very simplest method, So I prefer to go by this method. 2. Using Document Management...
View ArticleWant to map the Pre sales activities in SAP Project System.
Dear Expert, My client want to map some of the pre sales activities in the project system. Is it possible to map the below mentioned scenario in the SAP Project System module.Step by step process flow...
View ArticleRe: How to unblock time sheet data in PA2010 table
PA71 solved the problem. I really appreciate your help.
View Article