Re: sap ps and microsoft project integration
Hi Mandar, MSP is a widely used Project Management tool across globe.Through OPENPS4MSP you can easily integrate SAP PS with MSP.I suggest you explore OpenPS4MSP 4.0 and support your client in...
View ArticleRe: Preliminary Purchase Requisition for WBS
Hi guys this is what seems to be working for mein MRP2 put the in mrp4 put the information as in transaction OMD9 the results will be like
View ArticleRe: sap ps and microsoft project integration
Hi. This actually depends on the needs of the client. If they want to do detailed scheduling easily, and have s-curve etc.. it is actually easier and faster to to do it in MSP. The MSP also has the...
View ArticleRe: sap ps and microsoft project integration
Hi Mandar, Please check advantages of MSP:Widely Used tool for project managementEasy Integration with other Microsoft ProductsDesktop applicationintegration with SAP PS using Open PSIntegration:Open...
View ArticleBudget available report on released budget
Dear Experts, My requirement is I have allocated budget of 5,00,000 and I have release the budget for only 2,00,000 I have created a PR fro 50,000 In S_alr_87013558 report it is showing Available...
View ArticleHow to unblock time sheet data in PA2010 table
We transfer time sheet data to HR PA2010 table by CATA tcode. Due to authority issues, the data transferred blocked in PA2010 table. When the payroll works, blocked data is ignored. Is there a way...
View ArticleRe: How to unblock time sheet data in PA2010 table
I can think of 2 possible options:1. write an LSMW to remove the lock indicator, or,2. use transaction PA71, choose your infotype, then unlock.
View ArticleRe: How to unblock time sheet data in PA2010 table
Hi Bilgem, Is the data Locked / Unlocked ? If you dont have access, go to PA30 and check info type 2010 is locked. If there is access issue, you need to check or obtain the access required to access...
View ArticleRe: Intercompany resource related billing for projects
Hi Neeraj, Please note that any inter-company postings that are different from the invoicing flow might be illegal. I am not familiar with any situation when postings between legal entities are allowed...
View ArticleRe: Intercompany resource related billing for projects
Yes Paulo, I understand the document legality aspect of intercompany billing and will have corresponding cost and revenue recognized in alignment with documents. In nutshell you are recommending...
View ArticleRe: Intercompany resource related billing for projects
Hi Neeraj, Your understanding 1 to 5 is correct. CO-FI integration cannot substitute the invoicing flow, so why you would do it twice and taking the risk of postings through technical recon accounts?...
View ArticleRe: Intercompany resource related billing for projects
Paulo, I do understand the CO-FI integration is a separate topic , but we do have a use here. It will not substitute the billing process but should act as source to billing. I was just trying to use...
View ArticleRe: CAT2 error LR407 for Network posting
Hi Valentina, Never seen this message before as a starting point. What do you see at physical level in SE16 for CATSDB for those ****? If I remember that correctly for NWA you will not find a 4 digit...
View ArticleRe: Deletion of Automatic created Material reservation from SAP PS
Dear All,I have some issue with MRP run Date & plant delivery date, 01) Material Code is - XXXXX02) Planned Deliv. Time in MM03 (MRP-2) -...
View ArticleRe: CAT2 error LR407 for Network posting
Hello Paulo, I tried to delete the record but it is not possible, though I am able to add a new one with the same reference (activity/network/operation). The two records in CATSDB are exactly the same...
View ArticleRe: project builder giving error CJ 654 (information message)
Hello Sanjeev, Yes, in addition to training as suggested by Ken, You can ask them to change the CJ20N options so projects will be opened automatically in display mode, not in change mode Go to...
View ArticleRe: project builder giving error CJ 654 (information message)
Hi Ken,May be previos i am not able to addressing the issue to all of youbut let me elaborate more on it as we have 5 wbs two are locked from them. so now logistic user want to create milestone/any...
View ArticleRe: project builder giving error CJ 654 (information message)
Hi Sanjeev, You said its Information Message , not error message.So why are you worried? However using Message Control in SAP we can change category of some standard messages (like Error, Warning,...
View Article