Re: Availability control disappear in OK02 object type

$
0
0

Hi Lakshmi,

 

Unfortunately this note will not be applicable.

 

Can you please check whether the correction instruction mentioned by SAP is already available in your system ?  Since the note is about some modification, so i doubt whether this note is applied to your system.

 

Else you can also raise a OSS note to SAP relevant to this

 

Regards

Terence


Re: Availability control disappear in OK02 object type

$
0
0

Hi Maria,

 

Those notes are not applicable for our version.

Our SAP_APPL is SAPKH60015.

 

Is there any solution?

 

 

 

Regards,

Lakshmi.

Re: Availability control disappear in OK02 object type

$
0
0

Hi Maria,

 

Those notes are not applicable for our version.

Our SAP_APPL is SAPKH60015.

 

Is there any solution?

 

 

 

Regards,

Lakshmi.

Re: Availability control disappear in OK02 object type

$
0
0

Hi Lakshmi,

 

Just now i replicated the scenario using User Status

 

1. OK02

    DEAV Status with AVAC forbidden in business transaction

2. Assigned the Status Profile to Project Profile in OPSA

3. Budget Profile is defaulted to Project Profile

4. Budget Profile is Total Value / AVAC Activation is 1 with Overall value. (Hopefully any config should work if AVAC is 1)

5. Project Created having 2nd and 3rd WBS element (No AVAC)

6. Allocating Budget activated AVAC at all WBS element

7. Adding service to 3rd WBS element is working and able to add cost

 

Only thing i notice is the WBS element should have Budget, then it will work

 

Regards   

Terence

The problem of movt allowed indicator

$
0
0

Hello SAP folks,

We have encountered problems related to movt allowed indicator. the problem is when we do BOM transfer and then release the network/activity, for some components we find the movt allowed indicator is unticked , though the reservation can be seen and no further goods movement is possible due to this. Whereas for the other components through same BOM this problem is not there. Does this setting of Movt allowed indicator come from material master or by some other setting. How can goods movement be made possible for these, as customer requires to do goods issue for the reservation.

PS: I checked reservation settings from Transaction OMBN, but there also no such setting is maintained.

please guide

Regards,

Neha

Goods Issue to Production order in ProMan

$
0
0

Hi,

 

 

How to post goods issue to production order using ProMan.

 

Production order is created for making inhouse assembly. Assembly material BOM contents Raw material . This Raw material is procured and in CNMM (ProMan) it is appearing in Project stock.

 

However when material is being issued to production order/reservation,  the "Post goods issue (field)" appears in gray color. Hence not able to Post goods issue to production order.

 

Would like to know the process of goods issue in ProMan.

 

 

Thanks & regards

 

Vikram

Re: How to deactivate/disable (Project) activate button in Appropriation Request

$
0
0

Hello Saqib,

 

Please have a look in the IMG for Investment Management > Appropriation Requests > Master Data > Control Data.

 

You can exclude the whole tab second option: Specify tab layout...

You can also explore individual fields options with Define screen layout...

 

Regards,

Paulo

Re: Project Builder - User specific Options

$
0
0

Hello Jatinder,

 

Did you ever find a way to set the default setting (display or edit) for CJ20N? It is interesting that your posts asks for a way to default all users to EDIT while I saw another post that ask to default all users to DISPLAY. So, it appears possible to set either default for all users. I want to set to DISPLAY, while retaining the ability for an individual user to change their default to EDIT. Thank you for any assistance.

 

Regards,

Tom


Re: Settlement error repeats

$
0
0

Good Morning Suman,

have you had any joy resolving this as we are having the exact same issue.

During execution of settlement run in background whenever the message BP604 is correctly raised even once this message is repeated over and over again for a single WBS element.  This occurs even though the WBS element is only maintained as a settlement receiver once.

Restrict user to put Profit Center related to his Plant only in Network activity

$
0
0

Hi All Experts,

 

We have created 14 plants & each plant have 3-4 profit centers for an Investment type Project.

 

There are 6 levels of WBS elements & network header is assigned to 6 th level WBS.

 

Now our requirement is-

 

1. Particular user belonging to particular plant should not be able to put profit center belonging to any other plant while creating network activity(external Processing service activity)

 

2. System should restrict & throw error message on this.

 

3. Is there any enhancement/EXIT which will give user's plant data when we create network header/activity? so that we can put validation for profit centers.

 

Need your precious inputs in this.

 

Thanks in ADVANCE.

 

Regards,

ROHIT.

Re: Settlement error repeats

$
0
0

Hi Suman,

 

I guess this is due to different sender is different.

 

If you have a single sender, then it will display only one message.

 

Regards

Terence

Re: Include Resp. Cost center field in CN41 report through SAP Note 43493

$
0
0

Any pointers on it Experts?

 

Regards

Saurabh

Re: Restrict user to put Profit Center related to his Plant only in Network activity

$
0
0

Hi Rohit,

 

this can be achieved by Validation.

 

i have also done similar to your requirement in last project.

 

thanks

Sunil

Network activities confirmation error

$
0
0

When using report RCNVG000 and trying to confirm the activities of a network sometimes I get this error message: "No suitable object was selected" even though the activities are selected and seem fine.

collective_confirmation.png

This happens sporadically with different users and networks and they all seem OK.

 

What could be the cause of this?

RRB Billing DP93

$
0
0

Hi Gurus,

 

I have a situiation where 'Network' is appearing when I run DP93 but Network and corresponding WBS element is not populating in DMR?

 

Any thoughts pls.


Re: Batch Determination PS module

$
0
0

Hai Experts,

 

 

Can any one help me in getting a answer .

 

 

 

Regards

Mandan

Re: How to deactivate/disable (Project) activate button in Appropriation Request

$
0
0

Dear Paulo,

 

Can you please give more details as I could not find where I can make Project Activate button hide/display.

 

thanks

 

Saqib

Investment program Report for WBS

$
0
0

Hello X'perts,

 

Is there any report which shows -

 

1.Investment Program wise WBS.

 

 

I have tried all s_alr t-codes but apparently yet to get what I'm looking for.

 

Please guide.

 

rgds

Mazal

Re: How to deactivate/disable (Project) activate button in Appropriation Request

$
0
0

Hi Saqib,

 

Thats the standard layout, i doubt you cannot change it.

 

This particularly comes when you activate the WBS Element (Allowed Measure) in Appr. Request type.

 

If you dont want the screen, then it is simple to remove in OITO, or you need to do enhancement for the same screen S0017

 

Regards

Terence

Re: Investment program Report for WBS

$
0
0

Hi,

 

Please try being more specific regarding what are you looking for or what is missing...

 

S_ALR_87012805 - Structure Display for Investment Program should show both IM structure and investment measures (like WBS).

 

Regards,

Paulo